At its meeting on April 23, 2018, the City Council awarded the project to Ryan Contracting Company of Elko, Minnesota. A preconstruction meeting was held on May 1, 2018, at the East Fire Station, 6500 DuPont Avenue N, at which time residents had the opportunity to ask questions and meet with City staff and the Contractor. Construction has started and weekly construction updates, along with monthly newsletters will be added to this site throughout the project.
                
Project Details
Full street reconstruction with concrete curb and gutter
Partial Storm sewer replacement
Sanitary sewer replacement
Partial water main replacement

Contact Information
Please contact the following for all of your project coordination issues and information.
                       

Utility Outages
Please contact the following:
  • CenterPoint Energy (gas leak): 612-372-5050
  • Xcel Energy (electric outage): 1-800-895-1999
  • CenturyLink: 1-877-348-9007
  • Comcast: 1-800-934-6489
  • City of Brooklyn Center (water, sanitary, storm sewer, street lighting, or traffic signal systems) 7:00 a.m. to 3:30 p.m.:
         763-585-7100
         After hours call 911 (the dispatcher will contact the appropriate on-call service staff)
  •            
                                             

    Project Schedule

    October 24, 2017 - Neighborhood informational meeting held

    November 13, 2017 - City Council to receive feasibility report

    December 11, 2017 - City Council to conduct public hearing, authorize the project and order preparation of plans and specifications

    February 26, 2018 - City Council to approve plans and specifications and authorize the advertisement for bids

    April 23, 2018 - City Council to accept bids and award contract

    May 2018 - Start project construction

    November 2018 - Anticipated construction substantially complete
               
               
               







               
               








               










     Firehouse Project Area Map.jpg
                               Enlarge Map

    Project Information          
    Project History
               
    Preconstruction Meeting Flyer
               

               
    Construction Updates
    May 15, 2018
    May 21, 2018
    May 29, 2018
    June 8, 2018


    Newsletters
    May