69th Avenue Greenway/Cahlander Park Fence
Proposed construction includes replacing the wood fence along the north side of the 69th Avenue greenway between Brooklyn Boulevard and Palmer Lake Drive and the privacy fence on the west side of Cahlander Park. The City bid the project in 2016, but due to higher than expected bid amounts, it was determined to rebid the projects. Funding for staining the following year is also included as part of this project.
On May 19, 2017, a contract was awarded to Fenc-Co. Inc. for the Cahlander Park fence replacement, fence construction is complete with some turf restoration yet to be completed.
The 69th Avenue fence will be put out for bid in the fall of 2017 with an anticipated completion in June 2018. Based on contractor availability and the weather, some of the 69th Avenue fence may be completed yet this fall and the reminder will be done in the spring of 2018. The sealing of both fences will be completed before the winter of 2018.

Project Details
Replace existing wooden fence.

Contact Information 
763-585-7100 or
Utility Outages
Please contact the following for utility outages:                                   
  • CenterPoint Energy (gas leak): 612-372-5050
  • Xcel Energy (electric outage): 1-800-895-1999
  • CenturyLink: 1-877-348-9007
  • Comcast: 1-800-934-6489
  • City of Brooklyn Center (water, sanitary sewer, storm sewer, street lighting, or traffic signal systems) between 7:00 a.m. to 3:30 p.m. please call 763-585-7100. After hours, call 911 (the dispatcher will contact the appropriate on-call service staff).        
Project Schedules
September 29, 2017 - Quotations due.

October 9, 2017 - Contract awarded.

October 16, 2017 - Anticipated construction start.

June 2018 - Anticipated construction completed.